Capital Improvement Projects

The following is a summary list of active Capital Improvement Projects within the city limits of Hoover.  As individual projects progress, their status will be updated.  As projects are completed, they will be removed from the list. 


ALL PROJECTS AS OF September 25, 2019

Project Type Lead Agency Status Current Status (% 
​Complete)
Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Patton Chapel Road Improvement - Modifies two existing intersections into one, in front of Gwin Elementary School. Extends sidewalk along Patton Chapel Rd.  For additional information on this project, contact Jefferson County Roads
​and Transportation at (205) 325-5141.
Jefferson County Bid Process 90% Construction
12/19
Eden Ridge at S. Shades Crest Rd - Adds left turn lane to South Shades Crest Rd and realigns Shades Run Circle. ALDOT Construction 90% Completion 12/19
Galleria Blvd Extension - County lead project that extends Galleria Blvd. by Chick-Fil-A to Old Montgomery Hwy.  For additional information on this project, contact Jefferson County Roads​ and Transportation at (205) 325-5141. Jefferson County ROW Acquisition 50% Utility Relocation 10/20
Hwy 150 Right Turn Lane @ Whisperwood Ln City of Hoover Permitting Process 90% Construction 12/19
Valleydale Rd Widening (Little) - Widens Valleydale Rd to five lanes from Hwy 31 to Riverchase Parkway. ALDOT Design 95% ROW Acquisition 03/20
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. ALDOT ROW Acquisition
​94 Total tracts
​17 Pending​
85% Utility Relocation 01/20
Stadium Trace Pkwy at Brocks Gap Pkwy - Adds new turn lanes and extends existing turn lanes for each of the four intersection approaches. City of Hoover Construction
99% Completion 11/19
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes drive to Hwy 150.  (Awaiting Railroad approval)              Jefferson County      Permitting Process 50% Construction 12/19

SIDEWALKS, GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave. ALDOT ROW Acquisition
​30 Total tracts
​7 Pending 
80% Utility Relocation 12/19
Cahaba/Riverchase Greenway - Constructs parking, trail head and new trail on city-owned property adjacent to Riverchase Elementary school and the Cahaba River. City of Hoover Construction 50% Completion 12/19
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. ALDOT ON HOLD      
Bluff Park Sidewalks - Constructs sidewalks on multiple streets in Bluff Park. ALDOT Bid Process 45% Construction 01/20
Municipal Ln & Municipal Dr Sidewalks City of Hoover Bid Process 10% Construction
12/19
Alford Avenue Sidewalks, Phase 1 - Constructs sidewalk along Alford Avenue from Haden Street to Pine Lane and along Haden St from Alford Ave to Blue Ridge Blvd. City of Hoover Design 75% ROW Acquisition 10/19
Inverness Community Greenway - Constructs sidewalk and trail along Inverness Parkway from Valleydale Rd, through the City's Inverness Nature Park. (Awaiting environmental review) ALDOT Design
99% Construction 01/20

PARKS & FACILITIES

         
Bluff Park Pavilion - Replaces aging community center with a pavilion. City of Hoover Value Engineering      
Police Training Facility - Constructs new police training facility on Municipal Drive next to Fire Station 4. City of Hoover Construction 15% Completion 05/20
City Hall 3rd Floor Renovations - Renovate 3rd floor city hall administrative offices and Council Chambers. City of Hoover Bid Process 95% Construction 11/19
Star Lake Improvement - Upgrades Star Lake Park by creating one-way traffic around the lake, widening and replacing the existing sidewalk and improving parking. City of Hoover Value Engineering 15% Bid Process  

GENERAL / MISC

.
         
US Hwy 31 Street Light Replacement, Phase 2 - Installs new street lighting along Hwy 31 from Patton Chapel Rd to I-65. ALDOT Design

75% Construction
06/20
Traffic Signal Modifications Upgrade, Hwy 31 at Deo Dara Dr. City of Hoover
Equipment Procurement
50% Completion
12/19
Traffic Signal Addition - Stadium Trace Pkwy @ Flemming Pkwy City of Hoover Equipment Procurement   10% Construction      07/20
Marywood Drainage Improvements City of Hoover Bid Process 40% Construction 12/19
Upgrade Inverness Pump Station Telemetry City of Hoover Bid Process 50% Construction 10/19
Upgrade Riverchase Pump Station Telemetry City of Hoover Bid Process 50% Construction 10/19
Upgrade Woodford Pump Station City of Hoover Bid Process 50% Construction 10/19